1. Pipe, pipe fittings before bonding, the application of dry cloth to the socket side and socket outside the wipe treatment, when the surface sticky oil must be wiped clean with acetone.

The company is located in:

2. The cross-section of the pipe should be smooth and the vertical pipe axis should be chamfered. Before insertion, draw the marking line and try to insert it. The depth of test insertion can only be 1/3 ~ 1/2 of the original depth. When the clearance is too large, the adhesive method is forbidden.

The company is located in:

3. When applying adhesive, apply the inner side of the socket first and then the outer side of the socket after application. When applying the socket, apply the appropriate amount evenly from the inside to the outside in the axial direction. Do not overstress or over-apply (200g / m2).

The company is located in:

4. After the adhesive is applied, it is advisable to keep the applied external force constant within 1 minute, keeping the straightness and position of the interface correct.

The company is located in:

5. After the bonding is completed, the excess adhesive will be squeezed out in a timely manner, and shall not be forced or forcibly loaded during the curing time.

The company is located in:

6. Adhesive joints shall not be in the rain or water construction, may not operate below 5 ℃.

The company is located in:

7. Connection procedures: preparation → cleaning face → test insert → brush adhesive → bonding → conservation.